Active Tender Opportunities
Greater Vancouver Regional District (Metro Vancouver)
Greater Vancouver Regional District (Metro Vancouver)
Project: 25-252
|
06/23/2025 2:00 pm |
BC Ferry Services
Ministry Of Transportation & Transit
Ministry of Transportation and Transit
Project: 23040MJ0000
|
This project will see the construction of a new 104.5 m, two-span, two-lane Sackum Overhead No. 1491. The scope of work will also include roadway and highway construction including clearing, grubbing, stripping, pavement cutting, asphalt removal, roadway and drainage excavation, embankment construction, granular base supply and construction, barrier installation, drainage ditching and culvert installation. Removal of existing structure and temporary works included in the scope. |
06/24/2025 2:00 pm |
Ministry of Transportation and Transit
Project: 18090MJ0001
|
Construction of new bridge over Cusheon Creek. The construction of approximately 224 m of Fulford-Ganges Road, including safe dismantling and disposal of existing culverts to be replaced with a new 20 m, single span, two lane Cusheon Creek Bridge No. 10502, including construction of piled foundations, cast-in-place concrete abutments, supply and installation of precast prestressed concrete girders, supply and installation of waterproofing membrane and railings. Inquiries: [email protected]
|
06/25/2025 2:00 pm |
Ministry of Transportation and Transit
Project: 38517MJ0000
|
72.6 Lane Kms of Class B Graded Aggregate Sealcoat. The general nature of the work consists of the following: mobilization, quality management, traffic management, crack sealing, aggregate production, applying graded aggregate sealcoat, site clean-up and restoration. Inquiries: [email protected]
|
06/26/2025 2:00 pm |
Ministry of Transportation and Transit
Project: 26355MJ0001
|
The general nature of the scope of work to be carried out under the Contract consists of the following: Haul and installation of Revetment Riprap, supply and installation of culvert, haul and placement of base course gravels, removal and stockpile of HFSA, Type D excavation, bottom and top lift paving, removal, stockpile, and reinstallation of CRB, supply and placement of large woody debris, and revegetation seeding. |
06/27/2025 2:00 pm |
Ministry of Transportation and Transit
Project: 26323MJ0000
|
Returning the highway back to its previous state of 4 lanes. Build an MSE retaining wall as a berm and catchment and a cast-in-place concrete starter wall adjacent to the highway. Install 32 mm rock bolts and 75 mm anchors into the rock mass that are tensioned with concrete walers. Highway surface/road base repairs and drainage ditching following MSE wall installation and removal of temporary berm. |
07/03/2025 2:00 pm |
Ministry of Transportation and Transit
Project: 18081MJ0000
|
The installation of two precast concrete box culverts at Site 18080 and Site 18081 including stream channel enhancements and construction of approximately 157 m of the Renfrew Road approaches to the Site. |
07/03/2025 2:00 pm |
Ministry of Transportation and Transit
Project: 17207MJ2025
|
Rehabilitation consists of resurfacing and base repairs. Resurfacing involves 60mm miling with an additional 40mm asphalt overlay. Base reapirs of up to 1.2m depths. Inquiries: [email protected]
|
07/08/2025 2:00 pm |
Ministry of Transportation and Transit
Project: 25771MJ0000
|
The Work includes the removal of the existing 3 x 2100 mm corrugated steel pipe (CSP) culverts and the supply and installation of a 3900 mm structural plate CSP (SPCSP), a 2100 mm diametre relief culvert, inlet and outlet structures, debris deflector, dissipation pool and channel improvements. |
07/15/2025 2:00 pm |
Ministry of Transportation and Transit
Project: 18122MJ0000
|
Current scope of work includes a 700mm HDPE drainage pipe to convey water from Mini Road down to the shore, including a dissipation structure, and excavation of failures to increase slope stabilization. |
07/16/2025 2:00 pm |
Ministry of Transportation and Transit
Project: 18122MJ0000
|
Current scope of work includes a 700mm HDPE drainage pipe to convey water from Mini Road down to the shore, including a dissipation structure, and excavation of failures to increase slope stabilization. Inquiries: [email protected]
|
07/16/2025 2:00 pm |
Ministry of Transportation and Transit
Project: 38247MJ0000
|
Mobilization, traffic and quality management, CEMP, working office, deck survey, concrete deck scarification, partial and full depth repairs, deck joints and armoring, formwork/falsework for deck slab, reinforcing steel, bridge jacking/concerte bearing pedestal, bearing assemblies, steelwork, high pressure water blast clearing, supply/placement/curing of deck infill and overlay concrete, deck drains, approach asphalt paving, site cleanup and restoration. Inquiries: [email protected]
|
07/17/2025 2:00 pm |
Ministry of Transportation and Transit
Project: 25342MJ2026
|
Installation of inlaid durabable line markings for center line and lane lines on Highway 5N from Birch Island to Madd River, on Highway 1 from the Highway 97B intersection to Canoe, and lane line on Highway 5 from Merritt to the Helmer interchange. Inquiries: [email protected]
|
07/17/2025 2:00 pm |
Ministry of Transportation and Transit
Project: 26104MJ2025
|
Milling of centreline and shoulder rumble strips to prevent vehicles from leaving their intended lane of travel. Inquiries: Beau [email protected]
|
07/29/2025 2:00 pm |
Ministry of Forests
Ministry of Forests
Project: 215082
|
The Ministry of Forests (FOR) prepared a deactivation plan covering critical sites of Forest Service Road (FSR) that was realigned by FOR in previous capital projects. The purpose of this project is to deactivate critical sites of the legacy road and place them in a self-maintaining state. |
06/19/2025 11:00 am |
Ministry of Forests
Project: 215161
|
This project consists of installation of one 18.288 m steel girder superstructure, with composite concrete deck, on steel pipe risers and pre-cast concrete footings on the Finn-Tum FSR. Service will include the removal of the existing concrete slab girder structure, concrete cap beams and associated precast concrete footings and steel pipe risers. Service will include development, supply and placement of rip rap and completion of all new bridge approach road works including culvert replacement. Service will include delivery of existing concrete slab girders and associated abutment materials to the Clearwater Ministry yard. |
06/23/2025 2:00 pm |
Ministry of Forests
Project: 214330
|
Realignment and improvement of six (6) sections of road between 38km and 45km of the Cunningham Pass FSR (a.k.a. Matthew Valley Road). All 6 sections of improvements vary in complexity and design, with variable parent materials onsite. The design for this project includes multiple CMP installations and the removal of old CMPs. |
06/25/2025 2:00 pm |
Ministry of Forests
Project: 215209
|
Major Works Bridge Installation – 62-010A, 16 km Rosita-Meldrum FSR |
06/25/2025 11:00 am |
Ministry of Forests
Project: 215605
|
As part of an ongoing plan to upgrade the Cunningham FSR, a realignment project is the next phase. The Cunningham FSR is in the Stuart Nechako Forest District. The realignment is from 61.6km to 63.6 km |
06/25/2025 11:00 am |
Ministry of Forests
Project: EN26LMN233
|
Works involve activities on 11,850 lineal metres of various Forest Service Road (FSR) located in the Sea to Sky Natural Resource District. |
06/26/2025 11:00 am |
Ministry of Forests
Project: 215932
|
EN26474017 - Major Works - Project consists of four (4) bridge repairs and four (4) road repairs/reconstruction on the Arrastra FSR. |
07/03/2025 11:00 am |
Ministry of Forests
Project: 215545
|
This project consists of the installation of a 12m long 4.88m wide concrete slab bridge and a culvert. Service will include the removal of two existing culverts and reconstruction of the streambed. Service will include the development, hauling and placement of rip rap and completion of all new approach road works at site, including all grubbing and stripping. |
07/08/2025 2:00 pm |
Ministry of Forests
Project: EN26DRM0010
|
This is a Major Works contract for bridge repair of three bridges in the Bull River drainage, within the Rocky Mountain Natural Resource District. The bridge repair works are scheduled for summer to early Fall 2025 (mid July to late September). |
07/14/2025 9:00 am |
BC Timber Sales - Contracts
BC Timber Sales Branch
Project: EN26TEK496
|
The purpose of this contract is to complete a permanent road repair for Oliver Creek FSR at 1.7km. |
06/19/2025 2:00 pm |
BC Timber Sales Branch
Project: EN26TBH007
|
The purpose of this contract is to provide access to a future BCTS timber sale license, and involves the installation of two all-steel portable bridges, approximately 1428 meters of road reconstruction, and approximately 305 meters of new road construction. |
07/03/2025 2:00 pm |
Municipalities
Corporation of the Township of Esquimalt
Project: 215163
|
The supply of labour, materials, and equipment for the construction of sidewalks, bike lanes, and road rehabilitation on Esquimalt Road and Craigflower Road. The work includes underground utility renewals for storm and sanitary sewers using both open cut and trenchless methods, traffic signal upgrades and modifications, and the installation of Rectangular Rapid Flashing Beacons (RRFBs) |
06/19/2025 2:00 pm |
Village of Chase
Project: 1377-301-002
|
The Village of Chase invites tenders for the construction of Road Extension in the Shepard Road area of Village of Chase. A summary of specific work items includes the following (approx. quantities): • Approx. 2390m² of Hot- Mix Asphalt – 65mm |
06/19/2025 2:00 pm |
District of Metchosin
Project: 215894
|
• Cold Milling of approximately 3800 square meters, as marked in field. |
06/24/2025 2:00 pm |
District of West Vancouver
Project: RFP25 245
|
The District of West Vancouver ('the District') invites proposals from qualified contractors ('the Contractor') to provide maintenance services for the following bridge structures for the 2025 Bridge and Pier 1) STR No. 104: Almondel Road over Cypress Creek |
06/26/2025 2:00 pm |
City of Surrey
Project: 1724-005-11
|
2025 Intersection Improvements - Traffic Circles. This project is for the construction of three traffic circles with new curbs and sidewalks, stamped and colored concrete and asphalt, asphalt paving, temporary asphalt paths and curbs, drainage upgrades (including new catch basins, lawn basins, and a swale), new street lighting, and final landscaping. |
06/26/2025 2:00 pm |
City of Parksville
Project: 215767
|
The City of Parksville requests an Invitation to Tender for completion of pavement overlay, including various associated tasks. |
06/26/2025 11:00 am |
City of Surrey
Project: 1721-003- 21
|
The Owner invites tenders for the removal and replacement of Bear Creek Bridge on 140 Street. The work generally includes traffic control, detours, demolition and disposal offsite of the existing bridge, installation of piles and ground improvements, new abutments and girders, concrete decking, road widening, sanitary sewer and water relocations, erosion and sediment control, fish salvage, channel improvements in Bear Creek, topsoil, hydroseeding, planting and all other surface restoration work. |
06/26/2025 2:00 pm |
City of Langley
Project: 215938
|
The Owner invites Tenders for: Approximately 822 metres of 300mm diameter, 427 metres of 350mm diameter, and 27 metres of 250mm diameter watermain supply and installation including new water services and all appurtenances. |
06/26/2025 2:00 pm |
City of Penticton
Project: 215786
|
Through this Request for Proposal, the City of Penticton invites qualified contractors to submit proposals for the construction of utility upgrades and road reconstruction along Eckhardt Avenue, located between Main Street and Government Street. This work includes the associated surface and utility works along Government Street between Eckhardt Ave. E and Wade Ave. Substantial Performance for all Work should be achieved no later than August 1st, 2026. |
06/27/2025 2:00 pm |
City of Surrey
Project: 1722-001-11
|
Tenderers are invited for works under Contract No. 1722-001-11 involving roadworks construction of approximately 800m of 96 Avenue, including common excavation, imported granular materials, asphalt pavement, pavement marking & signage, new pedestrian and traffic signals, roadway lighting, retaining wall construction, sanitary trunk sewer and siphon works, storm works, surface drainage works, and landscape restoration. |
07/08/2025 2:00 pm |
City of Coquitlam
Project: RFP 25-010
|
The purpose of this RFP is to invite Proposals from professional, qualified, experienced companies for the provision of Minor Concrete Works Services on an “as and when required” basis. |
07/11/2025 2:00 pm |
Alberta
Cypress County
Project: AB-2025-04231
|
The scope of work for this project shall include, but is not limited to, the following: - Common Excavation including Topsoil Stripping Inquiries: [email protected]
|
06/26/2025 2:00 pm |
Town of Edson
Project: AB-2025-04226
|
This project involves the realignment of Wase Creek within the Town of Edson’s right-of-way, away from its current location. The work is divided into four stages: Inquiries: [email protected]
|
06/27/2025 2:00 pm |
Thorhild County
Project: AB-2025-04276
|
The scope work includes surface conditioning of gravel roads, involving the repair of soft yielding areas. The work includes subgrade preparation and stabilization using materials such as crushed gravel, geotextiles, geo-cell and chemical treatments. The materials are to be supplied by the County. The approach to reconditioning and stabilization will be determined on-site, utilizing the expertise of the Contractor in conjunction with the County agents/staff to address the extent and type of repair. This is seen as a collaborative approach in assessing the work. Inquiries: [email protected]
|
07/02/2025 2:00 pm |
Mountain View County
Project: AB-2025-04300
|
Schedule A – Guardrail, Range Road 13 & Township Road 302 Inquiries: [email protected]
|
07/03/2025 2:00 pm |
County of Grande Prairie
Project: AB-2025-04244
|
Range Road 125 from Twp Rd 732 to Twp Rd 742 The scope of work includes, but is not limited to, the following major types of work: Clearing and Mulching Inquiries: [email protected]
|
07/03/2025 2:00 pm |
County of Grande Prairie No 1
Project: AB-2025-04292
|
Range Road 53 from Twp Rd 712 south for 1.4km The scope of work includes, but is not limited to, the following major types of work: Clearing Inquiries: [email protected]
|
07/08/2025 2:00 pm |
City of Medicine Hat
Project: AB-2025-04287
|
Remove and dispose of existing asphalt pathways. Install new asphalt pathways along proposed alignments complete with landscape restoration. Construction Rehabilitation program including : Inquiries: [email protected]
|
07/08/2025 2:00 pm |
Yellowhead County
Project: AB-2025-04282
|
Yellowhead County would like to receive bids from qualified contractors for the repair of soft areas on various gravel roads in the County. Inquiries: [email protected]
|
07/08/2025 2:00 pm |
Transportation and Economic Corridors
Project: AB-2025-04213
|
Asphalt Concrete Pavement and Other Work 56:08 From 8 km South of Hwy 10 to 3 km South of Hwy 10 569:02 From Hwy 10 to 1.4 km South of Hwy 10 570:01 Hwy 569 to Hwy 848 841:02 Hwy 9 to 9 km South of Hwy 9 CENTRAL REGION APPROXIMATE QUANTITIES: 18,000 Square Metres Cold Milling Asphalt Pavement Contractor to supply all materials. Inquiries: [email protected]
|
07/10/2025 2:00 pm |
Transportation and Economic Corridors
Project: AB-2025-04245
|
BRIDGE CULVERT INSTALLATION AND OTHER WORK CENTRAL REGION APPROXIMATE QUANTITIES: 1 Lump Sum Excavation - Structural Contractor to supply all materials. Inquiries: [email protected]
|
07/15/2025 2:00 pm |
Bid Results
Project: EN24474048
|
Project: 5181309
|
Project: 14054MJ0000
|
Project: 24732MJ0000
|
Project: 25145MJ0001
|
Project: EN26TFM010
|
Contract Awards
Project: 186934
|
Project: 13004MJ0001
|
Project: 07-2025
|
Project: 210612
|
Project: 13265MJ2025
|
Project: EN26TKE034 - TOC
|
Project: 17107MJ2025
|
Project: EN26NAN600
|