Active Tender Opportunities

Ministry Of Transportation & Transit

Ministry of Transportation and Transit
Project: 38469MJ0000

Resurfacing project along Highway 37A using a Hot-In-Place Recycling system. The Project is located on Hwy 37A between Windy Point to Bitter Creek for approximately 30 km and on Hwy 37N from Meziadin Junction to Hanna Creek South Bridge, approximately 3 km. 

02/20/2025
2:00 pm
Ministry of Transportation and Transit
Project: 38101MJ0000

Replacement of Steel Stringers and Existing Timber Deck. The new deck will be wider than current and the approaches will be widened to accommodate this. A Soil Nail Retaining Wall will be installed at the Southeast corner of the bridge.

02/25/2025
2:00 pm
Ministry of Transportation and Transit
Project: 26574MJ0000

Full-width conventional paving on multiple locations on Hwy 1 between Regional Boundary and Gladwin Creek (28,700 Tonnes of Admix) (54.2 Lane Kms)

02/26/2025
2:00 pm
Ministry of Transportation and Transit
Project: 38320MJ0000

Construction of a roundabout intersection to replace the existing stop controlled intersection. The general nature of the work consists of the following: mobilization, quality management, traffic management, demolition and removals, excavation, installation, civil and municipal works, paving, concrete works, electrical, signing, and fencing.

03/11/2025
2:00 pm
Ministry of Transportation and Transit
Project: 14084MJ0001

Construction of two cast in place concrete retaining walls, removal of an existing modular concrete block retaining walls, Culvert Replacement, Traffic Management, Remediation of the embankments, shoulders, concrete barriers, and drainage channels, including installation of spillways and rip rap, supply and installation of signs and pavement markings.

03/13/2025
2:00 pm

Ministry of Forests

Ministry of Forests
Project: EN26DTR005

Forest Service Road Maintenance and Deactivation
Maintenece and Deactivation works on Forest Service Roads (FSR's) with the Thompson Rivers Forest DTR. Most of the work activities will be completed within the Kamloops area.

02/21/2025
10:00 am
Ministry of Forests
Project: 209663

The Ministry of Forests, Coast Engineering Group is legislated to maintain surface maintenance on Forest Service Roads. The Ministry of Forests has entered into agreement of providing routine grading maintenance to First Nations Communities.The Contractor shall provide the following Services:

This contract is for grading of the Canal Main FSR from station 0+000 to 45+000km and grade other FSRs AS AND WHEN NEEDED. There are no mob/de-mob cost associated with this contract. Price Per Unit is all found to complete works. Gradings are expected to be completed by the 15th of every month. Additional grading, may be requested by a Ministry representative, as required.

02/24/2025
2:00 pm
Ministry of Forests
Project: CS25LMN306

At any given time, there may be road maintenance projects (Forest Service Roads and Non-Status Roads) active within the Chilliwack District. To assist in the delivery of these projects the Chilliwack District is seeking a qualified and experienced forest road expert to deliver services identified in this Request for Proposal.

02/25/2025
2:00 pm
Ministry of Forests
Project: EN25LMN305

The nature of the proposed work is for “As and When” Forest Service Road Maintenance activities in the Chilliwack Forest District. The scope of the work includes, but is not limited to, mechanical and manual brushing, ditching, culvert maintenance and culvert installation and/or replacement, cross-ditch installation and/or maintenance, end-hauling, hand falling, grading, sign installation, and emergency road repairs.
The locations for road maintenance works are identified through road maintenance inspections and prescriptions by Ministry staff. The road maintenance works will be assigned on an “as needed” basis in accordance with the occurrence of situations evaluated as requiring “Forest Road Maintenance and Repairs” and deemed appropriate for action within the terms specified.

02/27/2025
2:00 pm
Ministry of Forests
Project: EN26DSN001

The work to be carried out under this contract may consist of the following:
• Spot surfacing and road gravelling
• Pullout construction, maintenance and/or extension
• Ditch and road slump repairs
• Culvert maintenance, replacement, and installation
• Road grading and packing
• Sign maintenance
• Gravel pit development
• Bridge installations, removals, or repairs
• Road deactivation and/or reactivation
• Beaver stop installation
• Snow plowing
• Danger tree removal and Right of Way brushing
• Grass seeding
• Minor road construction

03/06/2025
2:00 pm
Ministry of Forests
Project: EN26DTR004

Mechanical roadside brushing of Forest Service roads in the Thompson Rivers District.
The project is comprised of roadside mechanical brushing to protect the road prism and optimize visibility on each of the identified project sites.

03/11/2025
10:00 am
Ministry of Forests
Project: 209980

To replace 3 structures on FSR’s.
CK-2152A (Jones Lake FSR) is located at approximately 4.0km on the FSR and accesses rural residences and high value recreation sites.
CK-2358 (Lost Creek FSR) is located at approximately 3.0km on the FSR and is used to access rural residences and high value recreation sites.
CK-2166 (Lost Creek FSR) is located at approximately 5.0km on the FSR and is used to access rural residences and high value recreation sites.

03/20/2025
2:00 pm
Ministry of Forests
Project: MULRFQ26DSE001

The Ministry of Forests is seeking equipment services contractors who are interested in carrying out Heavy Equipment Forest Service Road Emergency repairs and as and when requested FSR maintenance within the Selkirk Resource District.
The services would consist of completing prescribed works using heavy equipment which may include, road prism stabilization, ditchline cleanout, culvert cleanout, replacement and/or inlet/outlet armouring, avalanche/landslide debris removal, end haul of gravel, rock, fill or waste materials, construction of waterbars, cross ditches or swales, hauling/placing riprap, minor bridge repairs, barricading roads and other works as deemed necessary by the Ministry representative.
To be eligible for Heavy Equipment Forest Service Road Emergency Work and as and when requested FSR maintenance, interested contractors must qualify for inclusion on a Qualified Suppliers List by submitting the requested response documents. A Qualified suppliers list will be used to distribute competition notices for FSR works described above in the Selkirk district.

03/31/2025

BC Timber Sales - Contracts

BC Timber Sales Branch
Project: RFQ26TGF001

BCTS has approximately 120km’s of road in the Robson valley that often needs unplanned maintenance. The purpose of this Solicitation is to create a contact list of interested suppliers that can supply road maintenance services within the Valemount and McBride operating areas. Minor construction and major structure installation work may be included as a part of the maintenance program. Maintenance projects will be issued on an as-and-when basis.

02/23/2025
10:00 am
BC Timber Sales Branch
Project: EN26TBP002

Upgrade of the existing Direct-to-Barge Ramp, construction of a new serge area, Wood Box culvert replacement with a 1800mm x 18m culvert, 0.098km of new road construction through a young regen stand and 0.916km of reactivation. All works are located on the Lena Lake Forest Service Road system in Hotham Sound.

02/27/2025
2:00 pm
BC Timber Sales Branch
Project: EN26TKE016 - TOC

The proposed Major Works contract requires the provision of forest road maintenance for various North Zone operating areas in the Okanagan-Columbia business area.

03/07/2025
11:00 am

Ministry Of Transportation & Transit

Ministry of Transportation and Transit
Project: 26561MJ0000

Hot-In-Place Recycling Highway 3 Sparwood to Alberta (45.0 Lane Km). Scope of work includes: Mobilization, Quality Management, Traffic Management and Control, Survey Layout, Aggregate Production, Signing, Asphalt Mix Design, Level Course, Joint Sealing and Site Cleanup.

02/25/2025
2:00 pm
Ministry of Transportation and Transit
Project: 38472MJ0000

Asphalt resurfacing on Highway 16 for approximately 23.0 KM from Fort Fraser to Engen BC. This project will incorporate a “Mill and Fill” strategy utilizing 15% Reclaimed Asphalt Pavement (RAP).

02/27/2025
2:00 pm
Ministry of Transportation and Transit
Project: 17162MJ2025

Combination of mill and fill, overlay, pulverization and resurfacing, South Vancouver Island.

02/28/2025
2:00 pm
Ministry of Transportation and Transit
Project: 38467MJ0000

Asphalt Surfacing 2025/26 Hwy 97 Simon Fraser Bridge to Sintich and Side Roads Scope of work includes: Mobilization, Quality Management, Signing, Traffic Management and Control, Survey Layout, Aggregate Production, Asphalt Mix Design, Cold Milling, Suppy and Appy Emulsified Penetrating Primer, Asphalt Base Corse, Asphalt Pavement, Pavement Drainage, Shouldering, Temporary Pavement Marking, Joint Sealing, Site Cleanup

03/04/2025
2:00 pm

Municipalities

Town of Qualicum Beach
Project: 209476

General contracting services for the Seacrest Place Slope Stabilization

02/19/2025
2:00 pm
City of Kelowna
Project: 209471

The City of Kelowna is seeking a qualified contractor for the construction of Glenwood Avenue urbanization between Richter Street and Ethel Street. This project includes a full road reconstruction to an XS-27 road cross section including paving, curb, sidewalk, boulevard, parking lanes, watermain upgrade, storm system installation, pavement markings, signage and overhead utility undergrounding.

02/20/2025
2:00 pm
District of Fort St James
Project: 209651

The District of Fort St. James is seeking proposals from qualified Proponents to provide quotes to re-pave/overlay 7th Ave west, 4th Ave west, 2nd Ave west, 6th Ave west, Douglas Ave, Dogwood Street, and Birch Street between August 1st and August 31st, 2025. Paving will consist of paving/overlay of a 50mm layer on top of existing asphalt, and shouldering of all streets paved. Water service lines are being replaced at each address but asphalt is only being removed for the excavation site, and not the entire street surface.

02/21/2025
1:00 pm
District of Invermere
Project: 209774

The DOI requires a contractor to perform the Prime Contractor role, to complete asphalt milling and overlay on selected road sections.

02/21/2025
1:00 pm
City of Dawson Creek
Project: 209354

The City of Dawson Creek invites contractors to submit a bid in response to Invitation to Tender 2025-05 - 2025 Capital Road Works Program - 100B Avenue – 8 Street to Wilson Road (Reconstruction) project, which consists of the following work:

• Full depth road reconstruction of approx. 240 lm of roadway
• Installation of approx. 200 lm of storm sewer c/w manholes and catchbasins
• Installation of approx. 145 lm of 1.5m wide sidewalk
• Replacement of water valve and hydrant assembly
• Approximately 100 lm of cured-in-place pipe (CIPP) liner installation for existing sanitary main

02/25/2025
1:00 pm
City of Coquitlam
Project: TENDER 73487

The City of Coquitlam invites tenders for Contract 73487 - Hornby Area Pavement Rehabilitation, generally consisting of the following, but not limited to:

Asphalt milling – Approx. 37,250 square meters
Asphalt Concrete Paving – 7,500 tonnes
Concrete curb and gutter – Approx. 40 linear meters
Thermoplastic Pavement Markings
Other miscellaneous and incidental work as contained in the Contract Documents.

02/25/2025
2:00 pm
City of North Vancouver
Project: 209498

The City of North Vancouver (“CNV”) is requesting responses to this Request for Proposal from qualified proponents with experience in the planning, feasibility analysis, design, and cost-estimating of park-supporting land bridges, also known as highway lids or caps. CNV is seeking a consultant team who can work collaboratively with CNV staff in exploring the feasibility of such a facility and its associated infrastructure.

02/27/2025
4:00 pm
City of Cranbrook
Project: 0956 0074 04

The Contract is generally for the following summary of Work:

• 2500m2 of full road reconstruction
• 235m of 150mm Ø C900 DR18 PVC Watermain
• 130m of 300mm Ø PP Storm piping
• 4-900mm Ø catchbasins and 1-1050mm Ø manhole
• 385m of mountable curb & gutter
• 345m2 of concrete sidewalk

02/27/2025
1:00 pm
District of 100 Mile House
Project: 364-8111

The Proponent is to include the following work that represents a base Proposal:

Design, construction and traffic control for a temporary bridge crossing and access roads as required for detouring. Inclusive of:
Coordination with Fortis BC for trenchless installation to relocate the existing gas main if required for the construction of the temporary bridge (gas work to be completed by Fortis and coordinated by Proponent)
Temporary sanitary force main relocation – Option A or B
Continuation of all other services as required
Demolition and removal of the existing Bridge structure
Permanent Bridge Construction
Permanent sanitary force main installation
Road restoration and asphalt repair
Work within a known archaeological boundary
Compliance with environmental permitting and archaeological monitoring requirements

03/05/2025
2:00 pm
City of Kelowna
Project: 210020

The City is looking to engage a qualified General Contractor to establish an early collaborative approach to problem-solving within the project. The primary objective is to address key constructability challenges and reduce uncertainty in the project scope during the design phase, before transitioning into the construction phase. The anticipated scope of work will include the remediation of the North and South dams at Turtle Lake Reservoir, including but not limited to the stripping of existing organics, construction of toe berms, extension of low-level outlet piping, and installation of piezometers.

03/05/2025
2:00 pm
City of Chilliwack
Project: 210292

Works include the removal of the existing bridge and replacement with a new clear span bridge complete with concrete filled steel piles placed behind the existing piles to help facilitate the re-construction/regrading of the banks following removal of the existing abutments. Restoration of the channel cross section. Replacement of the 600mm diameter storm main across McGuire Road. Road and bridge approach construction.

Provisional work - removing the culvert adjacent the east side of Banford Road along 48050 McGuire Road and 7036 Banford Road and daylighting Lindell Creek.

03/05/2025
3:00 pm
City of Kamloops
Project: 210083
03/10/2025
2:00 pm
District of Summerland
Project: RFP-2025-09

This Request for Proposals is an invitation by the District of Summerland to prospective Respondents to submit non-binding proposals for the Wharton Street Revitalization construction project, which can be briefly summarized as follows:

Corridor improvements from Victoria Road to Kelly Avenue along Wharton Street. These corridor improvements include sidewalk, multi-use pathway, road realignment, stormmain and attenuation tank and replacements.
Construction also includes park enhancements, landscaping improvements, creation of a public gathering areas along Henry Avenue between Main Street and Wharton Street, washroom facilities, pedestrian safety improvements and undergrounding of electrical and communications utilities.
Works also include watermain replacement along Victoria Road from Main Street to Wharton Street.

03/10/2025
2:00 pm
District of North Cowichan
Project: 210224

Herd Road Bridge Rehabilitation consisting of the following general scope: - Partial and full depth concrete bridge deck rehabilitation - Bridge deck joint replacement - South pier concrete diaphragm replacement - Bridge railing and approach barrier replacement - Watermain hanger replacement - Localized pile cap and piling repairs - Associated utilities and site works

03/18/2025
2:00 pm

Alberta

Alberta Transportation & Economic Corridors
Project: AB-2025-00708

TND0022362

Bridge Rehabilitation, Bridge Deck Waterproofing, Asphalt Concrete Pavement, Bridge Deck Joint
Replacement, Bridge Painting and Other Work
HWY507:02 BF75059 Carrying Hwy 507:02 over Mill Creek
kilometre 19.0 to 19.2 (EBL,WBL)

Southern Region

APPROXIMATE QUANTITIES:

1 LS Remove and Dispose of Existing Deck Joint Assemblies and Isolated Approach Slab and Concrete Parapet Removals
1 LS Deck Joint Assemblies - Supply, Fabrication, Delivery and Installation (B.F. 75059) Type 1 Strip Seal
720 M2 Surface Removal (B.F. 75059) Bridge Deck and Approach Slabs
10 Units Ultrasonic Impact Treatment - Isolated Bottom Flange Cover Plate End Termination Welds
1 LS Protection of the Environment (B.F. 75059) Isolated Steel Girder Overcoating Repairs
1 LS Protection of the Environment (B.F. 75059) Bearing Recoating
1 LS Surface Preparation and Painting (B.F. 75059) Isolated Steel Girder Overcoating Repairs
1 LS Surface Preparation and Painting (B.F. 75059) Bearing Recoating

02/27/2025
2:00 pm
Alberta Transportation & Economic Corridors
Project: AB-2025-00735

53:12 6 Km E of Hwy 855 to Hwy 36
kilometre 15.321 to 35.160
Removal and Disposal of Existing Bridge Structure, Cold Milling, Asphalt Concrete Pavement (ACP) and Other Work
56:16 Hwy 53 to 2 Km S of Hwy - 609 kilometre 0.010 to 21.767
Selective Grading, Granular Base Course (GBC), Cold Milling, Asphalt Concrete Pavement (ACP) and Other Work
609:02 Hwy 21 to West of the Village of Edberg kilometre 0.010 to 11.920
Subgrade Preparation, Granular Base Course (GBC), Asphalt Concrete Pavement (ACP) and Other Work
210:02 Hwy 56 to 1 km East of Hwy 56 - kilometre 0.000 to 1.365

02/27/2025
1:00 pm

Bid Results

  • Ministry of Forests
    03/05/2024
Project: EN24474048
  • HEAVY METAL MARINE LTD.
    $1,896,170
  • SURESPAN CONSTRUCTION LTD.
    $2,106,579
  • LANDMARK SOLUTIONS LTD.
    $2,304,430
  • BIG ROCK CONSTRUCTION COMPANY LTD.
    $3,122,630
  • Ministry of Forests
    01/07/2025
Project: 206132
  • DENIS FRANCOEUR BACKHOEING LTD.
    $617,348
  • ROC-STAR ENTERPRISES LTD.
    $685,499
  • 0813188 BC Ltd.
    $822,595
  • Far North Contracting Ltd.
    $830,000
  • SURESPAN CONSTRUCTION LTD.
    $842,916
  • PLATINUM STONE CONTRACTING LTD.
    $855,821
  • CALIBER BRIDGE AND DESIGN LIMITED
    $894,250
  • HEAVY METAL MARINE LTD.
    $954,583
  • BOREAL WEST FORESTRY LTD.
    $956,750
  • FORMULA CONTRACTORS LTD.
    $1,163,180
  • ENVIRO-EX CONTRACTING LTD.
    $1,250,000
  • Ministry of Transportation and Transit
    01/14/2025
Project: 26553MJ0000
  • City of Nelson
    01/14/2025
Project: 207891
  • Colas Western Canada Inc.
    $1,509,424
  • Ministry of Forests
    01/16/2025
Project: 207664
  • TWINCON ENTERPRISES LTD.
    $576,836
  • BOREAL WEST FORESTRY LTD.
    $727,120
  • CALIBER BRIDGE AND DESIGN LIMITED
    $745,285
  • ARNICA CONTRACTING INC.
    $887,700
  • DIG IT CONTRACTING LTD.
    $932,932
  • L.B. CHAPMAN CONSTRUCTION LTD.
    $1,120,608
  • SURESPAN CONSTRUCTION LTD.
    $1,226,917
  • CRL GROUP HOLDINGS INCORPORATED
    $1,262,999
  • QM LP
    $1,993,092
  • Ministry of Forests
    01/21/2025
Project: 208031
  • CALIBER BRIDGE AND DESIGN LIMITED
    $598,425
  • CHU CHO INDUSTRIES LIMITED PARTNERSHIP
    $822,316
  • BOREAL WEST FORESTRY LTD.
    $829,915
  • PLATINUM STONE CONTRACTING LTD.
    $870,832
  • NECHAKO EXCAVATING LTD.
    $944,585
  • Newland Enterprises Ltd
    $973,855
  • WEST HORIZON CONTRACTING INC.
    $1,326,825
  • Ministry of Transportation and Transit
    01/22/2025
Project: 26554MJ0000
  • PETER'S BROS. CONSTRUCTION LTD.
    $9,559,211
  • EMIL ANDERSON CONSTRUCTION (EAC) INC.
    $11,801,847
  • OKANAGAN AGGREGATES LTD.
    $12,702,831
  • Ministry of Transportation and Transit
    02/05/2025
Project: 26556MJ0000
  • OKANAGAN AGGREGATES LTD.
    $11,088,775
  • PETER'S BROS. CONSTRUCTION LTD.
    $11,214,211
  • Key-West Asphalt (332) Ltd.
    $11,312,100
  • LAFARGE CANADA INC.
    $11,458,348
  • Ministry of Transportation and Transit
    02/06/2025
Project: 38311MJ0000
  • ARC ASPHALT RECYCLING INC.
    $5,195,130
  • PETER'S BROS. CONSTRUCTION LTD.
    $5,311,211
  • GREEN ROADS RECYCLING LTD.
    $5,395,100
  • Ministry of Transportation and Transit
    02/11/2025
Project: 26557MJ0000
  • PETER'S BROS. CONSTRUCTION LTD.
    $6,274,211
  • GREEN ROADS RECYCLING LTD.
    $6,437,819
  • ARC ASPHALT RECYCLING INC.
    $6,501,273

Contract Awards

  • 04/11/2024 | 04/26/2024
    Ministry of Transportation and Infrastructure
Project: 13004MJ0001
  • $5,395,334
    MAYCON CONSTRUCTION MANAGMENT LTD.
  • 01/14/2025 | 01/28/2025
    Ministry of Transportation and Transit
Project: 26553MJ0000
  • $8,655,204
    EMIL ANDERSON CONSTRUCTION (EAC) INC.
  • 01/16/2025 | 01/31/2025
    Ministry of Transportation and Infrastructure
Project: 13254MJ0004
  • $8,322,009
    Jakes Construction Ltd.
  • 01/16/2025 | 01/29/2025
    Ministry of Transportation and Transit
Project: 38470MJ0000
  • $3,286,750
    WHITE BEAR INDUSTRIES LTD.